<aside> 🗺️

Owner: Tetiana Boliukh · Last reviewed: 27.08.2026 · Next review: weekly, Monday

This roadmap shows shape and sequence. It is not the system of record for day-to-day delivery — see Where the real numbers live below.

</aside>

How to read this

The timeline below is the January-2027 package: everything CareMaster and 10x have committed to for the pilot, laid out by owner and date.

A title prefix tells you something is not committed work:

Prefix Means
[Backlog — not contracted] Was in SO-003 "Evolved V1 Scope (Additions)". SO-003 is being withdrawn in its current form and its contents move to the backlog. Nothing here is signed, priced or scheduled. Dates shown are placeholders.
[Out of scope] Not part of the rebuild at all. The AI agents were estimated in April 2026 as investor-deck material and were never contracted.
[Backlog — not in the January package] In no current plan, bucket or estimate. Needs an explicit scope decision before anyone picks it up.
[Separate programme] Real work, different engagement. Trips is its own product and will have its own service order.

Anything without a prefix is in the package.

The delivery window

Estimate basis: 284 development days plus 20% QA, eight hours to the day, four developers (Vlad Sargsyan, Yaroslav Rudenko, Ilya Levin, Kurt McRae) plus Tracy Sergeev full-time on front end and Leonid Kornilov on QA at 50% across the window. Note that Kurt moves from full-time development to architecture and code review once the properties work ships, so the effective developer count drops during the window.

Where the real numbers live

This database is the shape of the plan. Three other places hold the detail, and they win where they disagree:

If a date here contradicts Linear, Linear is right and this page needs fixing. Tell Tetiana.


https://www.loom.com/share/a2b7c49c853c4d239718065add1ddc67

CareMaster RoadMap (V1)